New Florence, Pennsylvania
SCR Installations Units 1 and 2
Client / Owner
GenOn
Architect / Engineer
Sargent & Lundy LLC
Market
Power
Company
Graycor Industrial
Project Scope
GSL, a joint venture between Graycor Industrial and Sargent & Lundy, provided EPCM services for new selective catalytic reduction (SCR) systems at Units 1 and 2. Work included providing a pre-construction estimate and preliminary construction schedule as well as work package strategy and construction management.
GSL provided constructability input to the design and planning for installation of tie-in ductwork that took place during regularly scheduled unit outages in 2011 and 2013. The ductwork enabled the final tie-ins in 2014 to be completed with shorter outages.